Sunday, August 7, 2011

Day 174

Sunday = Rest Day (not that they need it they have not done alot)

Saturday, August 6, 2011

Day 173

No Work again Today, Starting to wonder what is happening with our front door.

Thursday, August 4, 2011

Day 171

Gyprock Sheets were Delivered to site today as well as the water tank was connected up





Wednesday, August 3, 2011

Day 170

We Met with the Site Manager today to get an update on what is to be happening with the house over the next couple of weeks, hopefully the doors get ftted soon as the house is now in "Lock Up Stage"

With in the next 2 weeks the gyprock will be up and the cornices cemented in with everything else ready to go.

So a possible end of September completion (we will see)

There was no actual work done on site today

Monday, August 1, 2011

Day 168

Water  Tank was delivered to site today, the colour matches the bricks well.