Tuesday, November 22, 2011

Day 281 (Week 41) [+57]

The Painter returned today do do a second coat on the front of the house, and he completed it just in time as the rain came tumbleing down... Also and FINALLY... they started to repair the bath tub in the main bathroom... just intime for our walk through tomorrow.



Monday, November 21, 2011

Day 280 [+56]

Workers were onsite today with a fair bit of work done to the outside. - Painter painted the downpipes and the front of the house (the right colour this time) the angle plates we installled above the doors and windows. and some trimming added to where it was needed on the balcony. Also the Expansion Joints were sealed and siliconed up!

they may just make it by wednesday for our PC walkthrough.....



Expansion Joints


Kitchen Window

Front Entry

Tuesday, November 15, 2011

Day 274 (Week 40) [+50]

Well Metricon decided to pull their finger out and actually organise some work for the house... the painter returned to site as well as the balcony guy to fix off the stainless steel barrier. Termite protection lookslike it was mostly installed too..

The Front looks nice now it is all stained again.



Termite Protection


Entry

Knock Knock


Porch


Saturday, November 5, 2011

Day 264 [+40]

wow 40 days over the original contracted date.. this is a very very disapointing milestone to reach, and it saddens me every time i look at the house...

But when i walk through it i am reminded how nice a house it is.. a shame the builders have no pride..

Today the Tilers were on site Grouting the floors of the wet areas.. the bathrooms are starting to look really good.

cant wait to see what they look like whennt hey are all nice and clean!!


Porch

Balcony

Balcony

Laundry

Main Bathroom

Thursday, November 3, 2011

Day 262[+38]

Tilers Returned to site today and they laid the tiles on our Balcony and Porch, the colours have tuned out really well.. They also grouted the tiles in the kitchen.




Tuesday, November 1, 2011

Day 260 (Week 38) [+36]

Tilers returned to site today and they laid the beds for the exterior tiles on the porch and balcony

The Glass on the front door was also replaced.

Porch

Balcony

New Glass in door

Monday, October 31, 2011

Day 259 [+35]

Today saw the balcony get fixed (I Hope) and the waterproofing re-done ready for tiling. The tassie oak dressing was also finished on the underside..

I do Really hope it is fixed properly this time


Tassie Oak Dressing

Balcony Repair


Balcony Repair

Water Proofing

Thursday, October 27, 2011

Day 255 [+31]

Today saw a carpenter onsite to start fitting off the door furniture also our electricity was connected the house is now alive!!


Power


Door handles


Wednesday, October 26, 2011

Day 254 [+30]

Today saw shower screens and mirrors go into our bathrooms, and they  have turned out pretty nice



Ensuite Mirror

Ensuite Shower

Main Bathroom Mirror

Main Bathroom Shower

Powder Room Mirrir

Monday, October 24, 2011

Day 252 [+28]

Today the Brickies finished the columns, this time the top was finished alot nicer as well.. howerver the carpenter returned and did some destruction moving the gable roof timber around to accomodate the fact that it was originally bult off centre.

Latley it seems there is mor steps backwards then there are forwards...



De-construction

another fixer upper

Saturday, October 22, 2011

Day 250 [+26]

Today saw the Plumbers return to site and install the bathtubs... if you can call what they did installing them.. the bathtups do not fit into the whole that was created for them.. something else for them to fix up.....

Brickie was also onsite setting up for monday to brick the top of the columns up. if the Carpenter fixed the problem... (doesnt look like they did as they still seem to be off.)

Thursday, October 20, 2011

Day 248 [+24]

Not alot done during the day today, the carpeters (6 of them) arrived late afternoon (5pm) to fix a problem with the timber support beams on our balcony, apparently they were off centre and it is preventing the brickies from continuing the column up.

What concerns me is why was this not picked up months ago when the columns where first bricked up??

It does make me wonder what other problems there are with the house that have been missed


Busy working

Wednesday, October 19, 2011

Day 247 [+23]

By recent standards of work onsite it was a quiet day, Brickies returned to site today and continued the columns up the front of the house as well as building the stairs in the Garage.