Public Holiday today so no work was completed on the house.
Showing posts with label Week 33. Show all posts
Showing posts with label Week 33. Show all posts
Monday, October 3, 2011
Sunday, October 2, 2011
Saturday, October 1, 2011
Day 229 [+5]
Friday, September 30, 2011
Day 228 [+4]
Thursday, September 29, 2011
Day 227 [+3]
Wednesday, September 28, 2011
Day 226 [+2]
Tuesday, September 27, 2011
Day 225 (Week 33) [+1]
With the contract build time technically completed and some work still to be finished, it is a little disapointing that they have taken this long to construct the house. it is not that far from completion but still they had enough time where rain days should not of made a difference
Some Stats over the 32 week Build
Rain Days = 16 (including 2 Sundays)
Days Worked on Site = 82
Days not worked on Site = 107
Public Holidays = 4
Sundays = 31 (they actually worked on 1 sunday too)
Onto Today......The tilers returned to site and they started on the wall tiles.. tiling the wals in the upstairs ensuite
Some Stats over the 32 week Build
Rain Days = 16 (including 2 Sundays)
Days Worked on Site = 82
Days not worked on Site = 107
Public Holidays = 4
Sundays = 31 (they actually worked on 1 sunday too)
Onto Today......The tilers returned to site and they started on the wall tiles.. tiling the wals in the upstairs ensuite
![]() |
| ensuite |
![]() |
| Feature wall in the Ensuite Shower |