Tuesday, October 25, 2011

Day 253 (Week 37) [+29]

No work on site today, nothing was Scheduled... Lucky as it Pelted rain all day... not that it should of made a difference as there is plenty of work to be completed on the inside still.


It is going to be a busy rest of the week.. "Practical Completion" is dues next week

Thursday, October 6, 2011

Day 234 [+10]

Once again no one was working on site.. but after the departure of the site manager, the "Construction Manager" was due to visit the site to see what needed to be done on the house.. (lots still)

It did rain a litle bit from 4:30pm onwards....

Sunday, October 2, 2011

Wednesday, September 28, 2011

Day 226 [+2]

Tilers returned to site today and completed the wall tiles in the Main Bathroom, Toilet, Downstars Powder Room and the Laundry. The Joins in the upstairs floor were also sanded flat.



Laundry Floor

Laundry Splashback

Powder Room

Toilet Floor

Main Bathroom Shower

Main Bathroom Bath

Master Bed Floor

Sunday, September 25, 2011

Day 223

Sunday today.. and it absolutly poured down all day.. good thing no one works today

Friday, August 19, 2011

Day 186

Nothing Again Today but it did rain the teeniest tiny amout....shouldn't of stopped work

Saturday, July 23, 2011

Thursday, July 21, 2011

Day 157

A Miserable wet Rainy day no work done today..i dont blame them i would not of got out of bed either

Saturday, July 16, 2011

Day 152

Rained a bit today but they managed to set up the facia boards and gutters around the Alfresco and Garage



Wednesday, June 29, 2011

Wednesday, June 15, 2011

Day 121

more rain.. and lots of it... no more work on the house... it is also very dark by the time i get there of an afternoon or evening now...

Tuesday, June 14, 2011

Day 120 (Week 18)

no work due to rain...... how that effects working inside i do not know....

Monday, May 30, 2011

Day 105

Absolutley Nothing..... it rained and got really really dark early


Saturday, April 30, 2011

Day 75

Rain + The day after the Royal Wedding + Saturday = No Work.........

Saturday, March 19, 2011

Day 33

Rain Rain go Away come again another day (after the house is finished!!)

no work today



we did however pit money down on the carpet for upstairs!!

Tuesday, March 15, 2011

Day 29 (Week 5)

No Changes today... except for a little bit of rain... no delivery either...



Thursday, March 10, 2011

Day 24

more upstairs frame work went up today as well as some of the garage and the Alfresco Roof Support Beams.. But Guess what came down.....Rain











And the view from the upstairs balcny will look a little something like this





Sunday, February 27, 2011

Day 13

a Light shower areound today not alot or rain though. No change to the site