Monday, April 11, 2011

Day 56

6 rows of bricks were added to the rear of the house today. it doesnt seem like much was done..


Sunday, April 10, 2011

Saturday, April 9, 2011

Day 54

Such a beautiful day and not a single worker on site.. there is alot of bricks left to be laid if they are going to be completed by next friday like the initial plan was.

Friday, April 8, 2011

Day 53

More Bricks were delivered to site today as well the gutters and facia parts. Also the rear of the house had more bricks laid.




Thursday, April 7, 2011

Day 52

today saw a few more rows of bricks go up around the Study/Laundry Corner of the house, it seems to be slowing down a little bit




The Air con Company also come to put in some of the droppers for our ducted air unit.

Wednesday, April 6, 2011

Day 51

Today saw te scaffold get completed aswell as the bricks continue along the Study/Laundry exteriors


Tuesday, April 5, 2011

Day 50 (Week 8)

Today chalked up half a century in construction days and there were no physical changes to the house, the brickies returned and set up on the first level of scaffold to resume the exterior wall.


Laundry Side


Rear of House


Front Portico


Almond Bricks Close Up