Monday, July 11, 2011

Day 147

Today saw 3/4's  of the scaffold come down around the house giving us the first look at some of the walls unobstructed

this also lets them finish of the roof on the alfresco and the garage



 Rear from Alfresco

Laundry Side of house 



Saturday, July 9, 2011

Day 145

Well What a suprise, today they house had some work done... well not some.. Alot....

The Tasmanian Oak was installed in the Main Gable, cladding was installed on the garage and laundry sides of the house, the eaves were finished on the main body of the house  and noggins were reinforced on the inside frame work





Friday, July 8, 2011

Day 144

No Work again today...

but a few deliveries, the gutters and facia delivered for the garage (and maybe alfresco) as well as the tiles for the garage (and alfresco)



Thursday, July 7, 2011

Day 143

suprise suprise no work again today..... its been almost 2 weeks since tools were on site. most likley no work tomorrow either... aparently there is a carpenter shortage and that is what is holding everything up....

Wednesday, July 6, 2011

Day 142

What seems to be the current trend at the moment, nothing was done onsite again.... starting to wonder if they ever going to do something.. might as well give up on them doing any work at all....maybe they think it is the block and we need to do work ourselves....