Thursday, July 14, 2011

Day 150

a mini milstone of sort today with 150 days racked up since ground was broken back in February

Today saw the majority of the cladding get fixed to the upstairs corners with a couple of small pieces left to be fitted off once the roof on the garage is completed.





Wednesday, July 13, 2011

Day 149

Today saw the Fall protection get delivered for the Alfresco and the Garage in preperation for the roof tilers to return to the site.  Additionally the carpenter Turned up late and finished the actual frame work (including the Gable) of the garage. (By the time the Gable was finished it was too dark to capture that on camera)


Day 148 (Week 22)

No Work on site today :(

Monday, July 11, 2011

Day 147

Today saw 3/4's  of the scaffold come down around the house giving us the first look at some of the walls unobstructed

this also lets them finish of the roof on the alfresco and the garage



 Rear from Alfresco

Laundry Side of house 



Saturday, July 9, 2011

Day 145

Well What a suprise, today they house had some work done... well not some.. Alot....

The Tasmanian Oak was installed in the Main Gable, cladding was installed on the garage and laundry sides of the house, the eaves were finished on the main body of the house  and noggins were reinforced on the inside frame work