a Light shower areound today not alot or rain though. No change to the site
Sunday, February 27, 2011
Saturday, February 26, 2011
Friday, February 25, 2011
Day 11
Today saw the start of the electrical go in, with what looks like the consumer mains and telecom conduiting along with i am assuming the 3 phase cabling to go with it.
Thursday, February 24, 2011
Wednesday, February 23, 2011
Day 9
No Change again today, but we were informed that external drainage works will start on monday with the frame starting to go up not long after that...the red on the slab is fading as well...
SO as there is not much happening while the slab dries out here is the ground floor and what it will look like
Tuesday, February 22, 2011
Day 8 (Week 2)
This time last week the block was just freshly cut... today no real changes apart from some enviromental barriers put up.
Monday, February 21, 2011
Day 7
Another Drying day today so nothing new, however the block looks a little sunburnt with a bit of a red colour developing on the surface.