Sunday, March 27, 2011

Day 41

Sunday = Rest Day = No Work = Lucy still doesnt have her kitchen Day


Saturday, March 26, 2011

Day 40

Today saw the plumbers return to site to complete a pressure test on the pipes, they also installed our exterior taps... We have Water Connected

It is Also  Looking a bit overcast too so hopfully the rain will stay away


"Front" Yard Tap


"Back" Yard Tap



Friday, March 25, 2011

Day 39

No Changes today, I am starting to wonder if anyone actually works on a friday i doubt anything will happen over the weekend too.. hope the weather stays ok.. i want to see the bricks started on monday so no rain please!!!

Thursday, March 24, 2011

Day 38

No Real Big Changes today, it does look like that someone went around and added some protection to the glass and frames of the windows and doors.

Wednesday, March 23, 2011

Day 37

Today saw the remaining windows get installed and some minor reinforcing to the frame officially finishing the framing up stage of the house.. with the rain recently the brick work will start on monday with approx 5 weeks of bricking to come.

Balcony Door

Our First Door Handle


The Balcony



Tuesday, March 22, 2011

Day 36 (Week 6)

No Changes today however i had a better chance to walk around the site an take some pics of the windows. tomorrow is a site meeting with the site manager.


Study Window


Kitchen


House Rear


Side of House

Monday, March 21, 2011

Day 35

It absolutly poured down today, yet onsite they still managed to get the windows in as well as the front balcony up.