No Changes to the site today... look forward to seeing what starts happening on monday
Saturday, February 26, 2011
Friday, February 25, 2011
Day 11
Today saw the start of the electrical go in, with what looks like the consumer mains and telecom conduiting along with i am assuming the 3 phase cabling to go with it.
Thursday, February 24, 2011
Wednesday, February 23, 2011
Day 9
No Change again today, but we were informed that external drainage works will start on monday with the frame starting to go up not long after that...the red on the slab is fading as well...
SO as there is not much happening while the slab dries out here is the ground floor and what it will look like
Tuesday, February 22, 2011
Day 8 (Week 2)
This time last week the block was just freshly cut... today no real changes apart from some enviromental barriers put up.
Monday, February 21, 2011
Day 7
Another Drying day today so nothing new, however the block looks a little sunburnt with a bit of a red colour developing on the surface.
Sunday, February 20, 2011
Day 6
Today was a "rest day" well not much you can do while the slab is drying and well it is sunday too.
so instead, today we went and purchased the tiles for the ground floor, a nice 600x600 porcelain number.
so instead, today we went and purchased the tiles for the ground floor, a nice 600x600 porcelain number.