One thing that has really frustrated and Annoyed me with Metricon is the lost time due to rain days.
They Claim just about everything over 0.4mm and it doesnt matter if they did infact work on that day, if it was a part day or a full day, external or internal work they will still claim it as there "may" or "may not" be an impact to the timeline where the rain "may" or "may not" cause a delay..
They also Claim Sundays and Public Holidays for the same reason that the rain just possibly "may" or "may not" cause a delay..
I mean they hardley even work a Saturday let alone a Sunday to even warrent claiming it as a lost time delay
It feels like just a cheap excuse to get them out of trouble..