Wednesday, June 29, 2011

Tuesday, June 28, 2011

Day 134 (Week 20)

Had a chance to look at all the electrical through the house and it appears to be mostly roughed in,  it appears that nothing else has been done around the house.

Monday, June 27, 2011

Day 133

A New day after the weekend and the electrician visited site with a rough in of the wiring and they installed our metre box




Saturday, June 25, 2011

Day 131

No Changes Today


Sun sits in a bad spot at a particulartime of afternoon... makes it hard for good pics.

Friday, June 24, 2011

Day 130

Today saw the flashing on the house get redone and completed ready for the weather board paneling to go up




Thursday, June 23, 2011

Day 129

Not Physical Changes today, but another delivery, what looks like the sliding door cavity for possible the Butlers Pantry





Tuesday, June 21, 2011

Day 127 (Week 19)

No work on site today but it was a delivery heavy  day with the cladding, the exterior doors and the Tassie Oak for the underside of the roof over the front porck





Sunday, June 19, 2011

Day 125

Sunday was a day of rest, but we managed to have a good look around, and we did notice that some stage a painter has been out and has painted under the eaves.. not sure when this was done.




also  noticed a very very nasty crack spanining 25 rows of bricks down the column.... guess that has to come down not too

Friday, June 17, 2011

Day 123

Today the "new" brickwork got a shower and have cleaned up really well




Thursday, June 16, 2011

Day 122

today saw some progress on the house after the bad weather, the "trimming" for the cladding was mostley installed



Wednesday, June 15, 2011

Day 121

more rain.. and lots of it... no more work on the house... it is also very dark by the time i get there of an afternoon or evening now...

Tuesday, June 14, 2011

Day 120 (Week 18)

no work due to rain...... how that effects working inside i do not know....

Monday, June 13, 2011

Saturday, June 11, 2011

Wednesday, June 8, 2011

Day 114

*cough* *Cough* all two of the brickies in the entire world were off sick this week so no work today again..


and its getting darker and darker earlier and earlier

Tuesday, June 7, 2011

Day 113 (Week 17)

a Massive effort on site today with absolutly nothing accomplished.....

it is disapointing to see the lack of work over the last month

Monday, June 6, 2011

Day 112

Some sand was delivered to site today, other then that a very disapointing nothing was done..........


Saturday, June 4, 2011

Day 110

today saw the brick layers (new brick layers) return to work to rebuild the front of the house


 This morning


after a days work




Friday, June 3, 2011

Day 109

Capping off the perfect week of nothing happening on site but apparently there is alot happening behind the scenes...


okay so i didnt make it to the house intime before it got pitch black.....

Wednesday, June 1, 2011