Monday, September 26, 2011

Day 224

Today is the official last day of the contracted build time.. from now on we go into adjusted time....still do not have a date for "practical completion" or a handover date....

But onsite today there was a flurry of work

the Tilers were busy in the bathrooms tiling all the floors.

The Carpenter Returned to do the down stairs Skirting and hang a few more doors including the Butlers Pantry Sliding Cavity and the Garage Internal Acces Door...

then all our Ceasar Stone Bench Tops were installed in the Kitchen, Bathrooms and Laundry.

Also the Kitchen Sink, the Laundry Tub and the Basins for the Bathroons were installed..

a Busy Busy day on site...

Still no Front door tho.


Downstairs "Powder Room"

Laundry

Hallway to Garage

Left Side Kitchen

Right Side Kitchen

Kitchen Island


Kitchen


Study

Upstairs Main Bathroom


Ensuite

Ensuite Vanity

Ensuite Tiles