Thursday, March 31, 2011

Day 45

More Brickwork today


Garage


Rear of House


Kitchen Garage Rear 


Garage Side


Wednesday, March 30, 2011

Day 44

Today was a busy day, the brickies continued to work bricking Bob's walls up (we decided to call the house Bob) well up untill it rained a little bit completing more of the side wall and starting on the rear of the house



Alfresco Side
(or "Al" Side as it is called by Lucy)


Rear of House


Kitchen Side


So Hopfully the final product will look like it was intended



Today we also selected our tiles for the bathrooms and kitchen the colours look a little like this:

Laundry and Kitchen Wall Tile


Bathroom Wall Tiles


Bathroom Feature Tile
(A Strip will run down in the shower)


Floor Tiles for Laundry and Bathrooms


 Outdoor tile for balcony and Portico


A very productive day with the Aircon sorted as well and a good quote on blinds and curtains to out fit the windows..

Tuesday, March 29, 2011

Day 43 (Week 7)

With the start of the 7th Week of construction, Today saw the brickwork started with 7 rows laid from the study around to the laundry





Under the Study WIndow


from the corner of the block


Close up of the Brick


Monday, March 28, 2011

Day 42

Today the Brickies arrived on site and started to set up to start on the exterior, also was a big clean up on site and our stairs arrived too









Sunday, March 27, 2011

Day 41

Sunday = Rest Day = No Work = Lucy still doesnt have her kitchen Day


Saturday, March 26, 2011

Day 40

Today saw the plumbers return to site to complete a pressure test on the pipes, they also installed our exterior taps... We have Water Connected

It is Also  Looking a bit overcast too so hopfully the rain will stay away


"Front" Yard Tap


"Back" Yard Tap



Friday, March 25, 2011

Day 39

No Changes today, I am starting to wonder if anyone actually works on a friday i doubt anything will happen over the weekend too.. hope the weather stays ok.. i want to see the bricks started on monday so no rain please!!!

Thursday, March 24, 2011

Day 38

No Real Big Changes today, it does look like that someone went around and added some protection to the glass and frames of the windows and doors.

Wednesday, March 23, 2011

Day 37

Today saw the remaining windows get installed and some minor reinforcing to the frame officially finishing the framing up stage of the house.. with the rain recently the brick work will start on monday with approx 5 weeks of bricking to come.

Balcony Door

Our First Door Handle


The Balcony



Tuesday, March 22, 2011

Day 36 (Week 6)

No Changes today however i had a better chance to walk around the site an take some pics of the windows. tomorrow is a site meeting with the site manager.


Study Window


Kitchen


House Rear


Side of House

Monday, March 21, 2011

Day 35

It absolutly poured down today, yet onsite they still managed to get the windows in as well as the front balcony up.

Sunday, March 20, 2011

Saturday, March 19, 2011

Day 33

Rain Rain go Away come again another day (after the house is finished!!)

no work today



we did however pit money down on the carpet for upstairs!!

Friday, March 18, 2011

Day 32

No Changes on Site today, but the windows will go in on monday and the bricky will start to set up on tuesday



in the mean time we have been told that any chipped bricks will not be used  and will be replaced....

fingers crossed still

Thursday, March 17, 2011

Day 31

Today was delivery Day with the Bricks and Windows Arriving to site


The brown Bricks have little chips along the edges, from transportation, when picking these through the selection period this never came up and i hope that this does not effect the appearance of the house.. it is a little bit worrying



And here are the windows