Sunday, July 31, 2011
Saturday, July 30, 2011
Friday, July 29, 2011
Day 165
Just as Quickly as it was delivered the Skip Bin has been Removed from Site again there is still a whole heap of rubbish on site tho
Thursday, July 28, 2011
Day 164
No real work today but a skip bin was delivered and the site cleaned up a little (there is a full bin and still lots of rubbish)
Wednesday, July 27, 2011
Day 163
No work again today...Apparently they are waiting for the frame inspector to check the framework....they might want to fix it around the front door first.....
Tuesday, July 26, 2011
Day 162 (Week 24)
Today saw work resume on site, with the ridge capping of the garage getting cemented into place and the alfresco roof getting tiled. with only a few tiles missing due to the fall protection brackets the roofing is just about completed!!
Garage |
Alfresco |
Monday, July 25, 2011
Day 161
No work today... a bit disapointing i would of thought for sure with the rain last week they would of finished what they didnt last week..
Plenty of other work happening in the street tho with a nother house having the ground broken. just no work on ours..
Sunday, July 24, 2011
Saturday, July 23, 2011
Friday, July 22, 2011
Thursday, July 21, 2011
Day 157
A Miserable wet Rainy day no work done today..i dont blame them i would not of got out of bed either
Wednesday, July 20, 2011
Day 156
Today saw the insulation get installed on the inside of the house...mostly
Bedroom 3 |
Master Bedroom |
Kitchen |
Tuesday, July 19, 2011
Day 155 (Week 23)
A miserable winters day today where i sweear it was cold enough to snow.....it did not stop the roof tilers, tiling the garage roof.
Garage Front |
Garage Rear |
Monday, July 18, 2011
Day 154
Today Saw the garage and Alfresco get the Facia and Guttering installed as well as the fall protection for the roof tilers. also we saw the Drain Pipes
Alfresco |
Garage |
Rear of House |
Sunday, July 17, 2011
Saturday, July 16, 2011
Day 152
Rained a bit today but they managed to set up the facia boards and gutters around the Alfresco and Garage
Friday, July 15, 2011
Thursday, July 14, 2011
Day 150
a mini milstone of sort today with 150 days racked up since ground was broken back in February
Today saw the majority of the cladding get fixed to the upstairs corners with a couple of small pieces left to be fitted off once the roof on the garage is completed.
Today saw the majority of the cladding get fixed to the upstairs corners with a couple of small pieces left to be fitted off once the roof on the garage is completed.
Wednesday, July 13, 2011
Day 149
Today saw the Fall protection get delivered for the Alfresco and the Garage in preperation for the roof tilers to return to the site. Additionally the carpenter Turned up late and finished the actual frame work (including the Gable) of the garage. (By the time the Gable was finished it was too dark to capture that on camera)
Monday, July 11, 2011
Day 147
Today saw 3/4's of the scaffold come down around the house giving us the first look at some of the walls unobstructed
this also lets them finish of the roof on the alfresco and the garage
this also lets them finish of the roof on the alfresco and the garage
Rear from Alfresco
Laundry Side of house
Sunday, July 10, 2011
Saturday, July 9, 2011
Day 145
Well What a suprise, today they house had some work done... well not some.. Alot....
The Tasmanian Oak was installed in the Main Gable, cladding was installed on the garage and laundry sides of the house, the eaves were finished on the main body of the house and noggins were reinforced on the inside frame work
The Tasmanian Oak was installed in the Main Gable, cladding was installed on the garage and laundry sides of the house, the eaves were finished on the main body of the house and noggins were reinforced on the inside frame work
Friday, July 8, 2011
Day 144
No Work again today...
but a few deliveries, the gutters and facia delivered for the garage (and maybe alfresco) as well as the tiles for the garage (and alfresco)
but a few deliveries, the gutters and facia delivered for the garage (and maybe alfresco) as well as the tiles for the garage (and alfresco)
Thursday, July 7, 2011
Day 143
suprise suprise no work again today..... its been almost 2 weeks since tools were on site. most likley no work tomorrow either... aparently there is a carpenter shortage and that is what is holding everything up....
Wednesday, July 6, 2011
Day 142
What seems to be the current trend at the moment, nothing was done onsite again.... starting to wonder if they ever going to do something.. might as well give up on them doing any work at all....maybe they think it is the block and we need to do work ourselves....
Tuesday, July 5, 2011
Monday, July 4, 2011
Day 140
No Changes on site today, but there are rumors the scaffold will be coming down at the end of the week (we will see.....)
Sunday, July 3, 2011
Saturday, July 2, 2011
Day 138
Its Saturday Again...and no work today....Again
we did find another crack though this time in the front of the right hand column.....