More Rain = No Work....
Tuesday, May 31, 2011
Monday, May 30, 2011
Sunday, May 29, 2011
Saturday, May 28, 2011
Friday, May 27, 2011
Thursday, May 26, 2011
Day 101
Nothing going up or coming down today.
the reason for yesterdays demolition... Apparently the Previous Bricklaying company Built the Front Entry Wall wrong and not to what was on the plans, so they had to bring it down to build it correctly.
a disapointing week as far as progress goes.
the reason for yesterdays demolition... Apparently the Previous Bricklaying company Built the Front Entry Wall wrong and not to what was on the plans, so they had to bring it down to build it correctly.
a disapointing week as far as progress goes.
Wednesday, May 25, 2011
Day 100
As we Crack the 100 days of construction the house took a major step backwards, i do not know the reasons why but the front wall around the entry and the door were removed (or torn down) leaving large piles of rubble on the front yard... a very large disapointment.
Tuesday, May 24, 2011
Day 99 (Week 15)
No Canges on site at the start of another week.... a teeny tiny bit of rain though
Next door however work began on the new two storey in the street with the land getting shaped we now have neibours on both sides
Monday, May 23, 2011
Sunday, May 22, 2011
Day 97
No Changes today,
but a closer inspection of the upstairs i noticed that the air conditioner ducts have been boxed in.
but a closer inspection of the upstairs i noticed that the air conditioner ducts have been boxed in.
Saturday, May 21, 2011
Friday, May 20, 2011
Day 95
With a big Happy Birthday to Lucy, the brickies (these are new brickies mind you) were onsite fixing up the little bits and pieces the brickies before hand got wrong with holes filled and the brick work under the doors redone it pretty much leaves the upstairs front section left to be done.
Thursday, May 19, 2011
Day 94
Today saw the return of the brickies to start finishing off the brickwork, the columns at the front of the house were finished along with the alfresco columns.
i am curious how they will get the lighting done on the columns at the front of the house
i am curious how they will get the lighting done on the columns at the front of the house
Wednesday, May 18, 2011
Tuesday, May 17, 2011
Monday, May 16, 2011
Sunday, May 15, 2011
Saturday, May 14, 2011
Day 89
Today saw the practical completion of the roof, with the tilers removing the fall protection barriers and fixong the remaining tiles into place.
Friday, May 13, 2011
Day 88
No Changes to the house but another delivery was dropped off, more bricks!! Hopefully they will finish the brick work around the alfresco columns now (not sure what is happening to around the upstairs balcony door, I think they forgot).
Thursday, May 12, 2011
Day 87
No Changes to the house today but the Bi-Fold Doors were delivered to site for the alfresco doorway in the family room
Wednesday, May 11, 2011
Tuesday, May 10, 2011
Day 85 (Week 13)
With the start of week 13 the roof tilers returned to finish the portion of the ridge capping they didnt do yesterday.
Monday, May 9, 2011
Day 84
The Tilers returned today to seal and paint around the ridge capping, but they only managed to complete 3/4's of the roof.
Sunday, May 8, 2011
Saturday, May 7, 2011
Friday, May 6, 2011
Thursday, May 5, 2011
Day 80
Today saw the roof tilers return to site and cement in the ridge capping just about finishing the roof off.
Wednesday, May 4, 2011
Day 79
No changes at the house today so for something different here is what the house looks like in the dark!!